More Details On Beach Replenishment
There has been significant progress with the beach fill project around the 20th Street area of [...]
There has been significant progress with the beach fill project around the 20th Street area of [...]
Stone Harbor Representatives attended the Weekly progress meeting with state and federal officials, and Great Lakes [...]
Due to a weather conditions that moved into our area over the weekend which predicted 4-5 [...]
The Bay Dredging Project is complete! Sevenson, the contractor, completed the dredging last week and removed [...]
The southernmost portion of the Stone Harbor Beach Replenishment Project, the area from 123rd to 105th [...]
Volunteers should meet at 96th Street beach at 9 am. Bret Dunlap will be the SHPOA [...]
The Bay Dredging project is 77% complete with 74,912 CY dredged as of March 8th. South [...]
Stone Harbor Mayor Judith Davies-Dunhour, Council Members Joselyn Rich and Ray Parzych, Administrator Jill Gougher, Public [...]
This update provided by SHPOA Beach & Bay Committee The dredge “Texas” arrived February 14th, 2017 and [...]
Officials from Avalon and Stone Harbor attended the weekly progress meeting for the upcoming beach [...]